The Gratacon Team

Expanding emergency power capacity in an active research environment.

As electrical demands grew at NLR’s Solar Energy Research Facility (SERF), its emergency power infrastructure needed to keep pace. Gratacon served as general contractor for replacing the existing emergency diesel generator with a larger-capacity unit, strengthening backup power for current operations and future growth.

The $1.96 million project involved generator replacement, associated electrical panel and conduit work, and tie-ins to existing building infrastructure on NLR’s South Table Mountain campus in Golden, Colorado. Delivering that work required advance procurement, carefully coordinated shutdowns, and close communication with the people responsible for keeping the laboratory operating safely.

Planning Around Life Safety and Facility Operations

Emergency power plays an important role in protecting building occupants and supporting safe operations during a power outage. Replacing that infrastructure within an occupied research facility required careful attention to how construction activities and electrical shutdowns could affect the building.

Gratacon began coordinating shutdown logistics nearly a year in advance. Working with NLR’s facilities personnel, technical representatives, and an electrical trade partner, the team planned the work sequence. It coordinated the tie-ins needed to connect the new equipment to existing infrastructure. Ongoing communication helped the team understand operational priorities and minimize construction impacts on facility users.

Driving Procurement Before Work Started

Required equipment had long lead times, making procurement central to the project’s success from the start. Our team coordinated submittals, purchasing, and material tracking early, linking equipment availability to the planned construction and shutdown sequence.

That preparation became particularly important when electrical panel procurement raised concerns about an upcoming shutdown. Gratacon maintained close follow-up with the electrical contractor and NLR to track delivery and coordinate the work around equipment availability. Those efforts helped the team maintain the planned shutdown date.

Coordinating Technical Work in an Existing Building

The project required coordination among NLR’s technical representatives, facilities team, and trade partners. Existing conditions and owner installation expectations required responsive communication as work progressed.

Gratacon’s project management and field leadership worked together to address questions, coordinate installation activities, and resolve issues with the owner and trades. This connection between procurement, field execution, and facility operations was essential to managing the work within a live laboratory environment.

Supporting the Facility’s Next Chapter

The completed upgrade increased SERF’s emergency generation capacity to better meet its growing electrical needs. Just as important, the project demonstrated the planning and coordination required to replace critical infrastructure in an operating research facility, with life safety and facility users’ needs central to the work.

Project Partners: Denver Electrical Contractors and Caliza Concrete